Rapid EIA study in connection with the expansion of the mill from 75,500 tpa to 160,000 tpa (1996)Technical and engineering services including project management for mill expansion-cum-modernisation programme (120,000 tpa), involving design engineering for India’s first ECF pulp mill (1998)Parallel operation of 12 MW and 5.5 MW turbo generator set integrating with pressure reducing station (1998)Detail engineering and technical consultancy services for installation of a second-hand duplex board machine at Central Pulp Mills, Gujarat (On-going)