Technical audit and mill development study of 7200 tpa fine paper mill based on straw and grass (1995)
Techno-economic feasibility study for installation of a captive co-generation power plant (1998)
Energy audit (1999)
Installation of 6 MW TG set along with 35 tph AFBC boiler for the new co-generation plant (2001)
Engineering and consultancy services, procurement assistance, project management services and assistance in construction management for installation of a 35 tph FBC boiler and 5 MW turbo alternator for captive co-generation power plant (2001)
Techno-economic feasibility study for expansion/diversification into industrial sector (2004)
Techno-economic feasibility report for expansion of the mill by installing a newsprint machine (2005)
Rapid EIA study in connection with the proposed paper machine #3 and power plant of the mill (ongoing)
Project engineering and technical services for implementation of mill development plan involving installation of a paper machine (PM#3), fibre preparation and utilities (ongoing)